Total Project Cost PhP 3,419.446 M
GOP PhP 363.897 M
Loan PhP 2,607.613 M
LGU PhP 291.161 M
ARC PhP 156.775 M
  The project aims to continue the momentum achieved by ARCDP I in program beneficiaries development and support delivery directed at increasing farmers' income and providing further opportunities for sustainable growth and poverty reduction. ARCDP II also promotes the expanded role and capacities of local institutions, particularly LGUs, in managing and sustaining local rural development initiatives and programs. In broader framework, the ARC development shall be integrated and linked with local priorities and directions of identified SAFDZs in the project areas. These objectives shall be achieved through the synergistic application of 3 major components: community develoment and capacity building, agriculture and enterprise development, and rural infrastructure.
Components
  • Community Development & Capacity Building (CDCB)
  • Rural Infrastructure (RI)
  • Agricultural & Enterprise Development (AED)
  • Support to Rural Finance (SRF)
  • Project Management
Source of Funding   World Bank (IBRD Loan #7152)
Project Duration   4 years (June 2003 - June 2007) Extended December 2008
Target No. of ARCs   127 ARCs in 18 provinces
Target No. of Beneficiaries   85,000 ARBs  
     