LOGICAL FRAMEWORK OF SPOTS PHASE II

 
NARRATIVE SUMMARY
OBJECTIVELY VERIFIABLE INDICATORS *
MEANS OF VERIFICATION
RISKS/ASSUMPTIONS
GOAL
.
 
1. Poverty reduced 1.1 Reduce the proportion of the population living below the poverty line in 44 un-energized ARCs in Mindanao by 2% per year starting in 2007 1.1.1 Baseline survey
1.1.2 Impact evaluation reports
1.1.3 Minimum basic needs (MBN) surveys
before and after project
1. Support services provision to ARCs/ARBs remains a top priority in agrarian reform even after scheduled termination of CARP in 2008.

2. Major strategies on the peace process are vigorously pursued to create synergy with agrarian reform and generate impact in ARCs with security concerns.
PURPOSE      
1. Improved delivery of basic social services
1.1. Increase number of newborns immunized with BCG, DPT, MMR and polio vaccine in 44 un-energized ARCs in Mindanao by 20% from 2006-2009

1.2 Increase number of pregnant women immunized with Tetanus Toxoid in 44 un-energized ARCs in Mindanao by 10% from 2006-2009


1.3. Increase number and types of teaching methods or approaches employed in elementary schools in 44 un-energized ARCS in Mindanao by 20%from 2006-2009

1.4. Decrease in time spent (mins./day) for fetching water in 44 un-energized ARCs in Mindanao by 65% from 2006-2009

1.5. Increase number of households with access to potable water in 44 un-energized ARCs in Mindanao by 65% from 2006-2009

1.6. Reduce Incidence of water-borne diseases in 44 un-energizedARCs in Mindanao by 20% from 2006-2009
1.7 Increase proportion of employed in the labor force in the project sites in 44 un-energized ARCs in Mindanao by 5% per year for three years

1.8. Increase in time devoted to economic, social, recreational activities and children's studies in 44 un-energized ARCs in Mindanao by 20% from 2006-2009

1.1.1 Baseline surveys
1.1.2 Project completion review report
1.1.3 Annual and semestral
progress reports
3. HHs have the capacity to pay for use of various solar systems to sustain O&M of these facilities.

4. LGUs sustain their commitments to pay for the O&M of communal facilities.

5. Willingness to pay for tariff in electricity and water of the beneficiaries.

6. Markets remain favorable for outputs of rural enterprises to sustain their profit levels and enhance HHs' capacity to pay for use of solar facilities.

7. Unfavorable climatic conditions do not disrupt operations of agri-based enterprises.

8. LGUs' commitment to the project is not compromised by changes in local leadership.

2. Productivity (farm and non-farm) increased and sustained
2.1. No. of HHs adopting new, improved, or appropriate technologies increased in 44 un-energized ARCs in Mindanao by 50% from 2006 to 2009

2.2. Yield levels of agri-based and non-agri-based enterprises increased in 44 un-energized ARCs in 20% from 2006 to 2009

2.3. Raise household income of ARBs in 44 un-energized ARCs in Mindanao by 2% per year from 2006 to 2009
2.1.1 Field surveys (including market surveys)
2.1.2 Project progress
monitoring reports
3. Local organizations capacitated 3.1. 75% of the required O&M costs in 44 un-energized ARCs are paid in 3 years

3.2. 60% of the required O&M cost is deposited in a bank in 2 years in 44 un-energized ARCs in Mindanao from 2006 to 2009

3.3. 50% of the total number of POs increase their OM rating by one level in 44 un-energized ARCs in Mindanao from 2006 to 2009

3.4. Increase in the proportion of women involved in PO activities in 44 un-energized ARCs in Mindanao by 20% from 2006 to 2009 3.5 Increase the POs capital in 44 un-energized ARCs in Mindanao by 20 % from 2006 to 20093.6 Increase the total savings of POs in 44 un-energized ARCs in Mindanao by 10 % from 2005 to 2009

3.7 Increase total assets of PO in 44 un-energized ARCs in Mindanao by 10 % from 2005 to 20093.8 Increase the net income of PO in the 44 un-energized ARCs in Mindanao by 5 % per year
3.1.1 PO records
3.1.2. Annual ALDA/OMA reports
3.1.3 Project progress reports
 
OUTPUTS      
1. Solar power-driven facilities installed. 1.1. Energize and equipped 90 Barangay Health Centers with vaccine refrigerators in 44 un-energized ARCs in Mindanao

1.2. Energize and provide 115 schools with TV-DVD and educational CDs in 44 un-energized ARCs in Mindanao

1.3. Energize 32 Solar electricity-generated Level II potable water supply systemsin 44 un-energized ARCs in Mindanao
1.4. Provide 9,500 SHLS to HHs in 44 un-energized ARCs in Mindanao1.5 Energize 75 Barangay Halls in 44 un energized ARCs in Mindanao
1.6 Provide 200 Community Lighting Systems
in 44 un-energized ARCs in Mindanao
1.7 Provide 15 AC 10 Power Block of Energy in 44 un-energized ARCs in Mindanao

1.8 Energize 18 Solar electricity-generated agri in 44 un-energized ARCs in Mindanao
water systems
1.9. Power availability in 44 un-enrgized ARCs in Mindanao by 60% from their baseline levels 1.10. Total number of energized HHs in 44 un-enegized ARCs in Mindanao increased by 60%
1.1.1 Field inspection/validation reports
1.1.2 Certificate of project
completion
1.1.3 Project progress reports
9. Security situation in the ARCs do not hamper the timely delivery, installation, and commissioning of the solar packages.

10. Unfavorable weather conditions do not aggravate inherent difficulties in the delivery of solar packages in view of the remote locations of the recipient ARCs

11. Integrity of waivers from NPC, NEA, and RECs on non-electrification of project ARCs within 5 years after solar energization is not compromised by political interventions and other external factors.
2. Agriculture and rural enterprise development initiatives implemented 2.1. Established 40 techno-demo farms/enterprises in 44 un-energized ARCs in Mindanao in two years

2.2. Forged 15 marketing agreements for products of enterprises in 44 un-energized ARCs in Mindanao

2.3. Installed Income Generating Activities to 75% of SHLS beneficiaries in 44 un-energized ARCs in Mindanao

2.4. Established 18 AC-10 anchored rural enterprises in 18 un energized ARCs in Mindanao

2.5. Established 15 agriwater anchored high-value crop/nursery production projects in 15 un-energized ARCs in Mindanao

2.6. Established 15 new non-solar rural enterprise projects in the 44 un-energized ARCs in Mindanao

2.7. Develop 80 income-generating projects in 44 un-energized ARCs in Mindanao

2.1.1 Project Progress Reports
3. Organizational development and strengthening of new and existing POs/Coops carried out.
3.1. 100% of POs have set-up their organizations in 44 un-energized ARCs in Mindanao 2 years

3.2. 100% of POs in project areas with Policies Systems and Procedures in 44 un-energized ARCs in Mindanao in 2 years 3.3. 100% of POs with books of accounts in 44 un-energized ARCs in Mindanao in 2 years

3.4. 80% of POs are registered with either DOLE-BRW, CDA or SEC in three years in 44 un-energized ARCs in Mindanao

3.5. 75% of POs with active bank accounts in two years in 44 un-energized ARCs in Mindanao
3.1.1 Field monitoring reports
3.1.2 Project progress reports
3.1.3 PO records
 
INPUTS      
1. Solar Electrification

a. Technical validation for SHLS

b. Conduct of technical trainings



c. Solar Package Feasibility studies

d. Installation, commissioning and hand-over of solar packages


9,500 HHs validated for SHLS installation

3-tiered technical trainings conducted, viz:
Level I trainings
Level II trainings
Level III trainings

100% of POs have been trained on the technical aspects of solar projects

44 Solar Package Feasibility Studies prepared

Installed Solar Packages
9,500 SHLS
32 potable water supply systems
90 barangay health center packages
115 school systems
75 barangay hall systems
200 community lighting systems
15 agriwater systems
18 AC 10 block of power systems



Project Progress reports


Training and post-training reports




Installation Data Sheets
Installation Data Sheets


Approved Feasibility Studies

Hand-over certificates
Certificate of project completion

12. Security situation in project sites do not hinder installation works
2. Agriculture and Rural Enterprise Development

a. Agribusiness development plans and enterprise development plans

b. Agribusiness Feasibility Studies

c. Cross-visits to ARCs

d. Conduct of trainings on agricultural technologies


e. Market linkaging



40 agribusiness development plans prepared

15 enterprise development plans prepared

15 agribusiness feasibility studies prepared


15 cross-visits to other ARCs organized

100% of POs trained on appropriate agriculture technologies and/or rural enterprises

15 market matching/linkaging initiatives implemented




Training and post-training reports
Field monitoring reports

 
3. Institutional Development

a. Conduct of Social Preparation

b. PO assessment

c. PO formation


d. Institutional Development Plans

e. Institutional Development
Trainings

40 municipal orientations conducted
80 barangay orientations conducted


88 POs assessed

POs formed in 100% of sites without existing POs

16 institutional development plans formulated


100% of POs in project areas have been trained on:
a) Organizational Management
b) Financial Management
c) Project Management
   
4. Project Management

a. Management offices





b. Committees

c. Implementation Manual


e. Approval of nominated sites

f. SAC meetings organized

g. Year end Assessment conducted

h. Sustainability Planning conducted

i. FS training conducted

j. MOAs with LGUs on O&M of social/ communal packages

k. Monitoring and Evaluation


2 PMOs (based at DLR and DOE) reactivated@
1 new RPFOs organized; 5 RPFOs reactivated@
4 new PPFOs organized; 11 PPFOs reactivated@

3 committees (PSC, SAC, SES) reactivated@

Implementation manual containing 8 distinct
Implementation Guidelines updated@

150 sites in 44 ARCs identified

12 meetings held

2 assessments


1 planning workshop


1 FS training

44 MOAs with 44 LGUs prepared and executed

1 baseline data document
1 proj. completion review report for Phase II
1 impact evaluation report (inclusive of Phases I and II)



MOU issued
Special Orders issued
Special Orders issued
Progress Report


13. DLR field offices remain committed to detail
personnel to the project.