| INTERVENTION
LOGIC |
OBJECTIVELY
VERIFIABLE INDICATORS |
SOURCES
OF VERIFICATION |
ASSUMPTIONS
& RISKS |
| Overall
Objective
Poverty alleviated amongst the ARBs nationwide (14 regions) |
|
-
Beneficiary
income surveys (project years) compared against baseline
survey (project y1)
-
Project
review/evaluation reports
-
GOP
statistics and poverty indicators
|
|
| Project
Purpose
Increase the self-reliance, living standards and quality of
life for all households actively farming within 79 ARCs nationwide. |
-
Average
household incomes increased in each ARC by 30% at the
end of the y6 of the project.
-
Increased
agricultural diversification and production
-
Increased
support infrastructure and basic needs fulfillment
|
-
Project
Internal M&E comparing baseline surveys levels against
impact surveys in y5.
-
Internal
monitoring of yield, area, cultivated, diversification
and physical construction.
-
External
evaluations GOP statistics and/or PBME.
-
Participatory/self
evaluation reports of peoples's organizations and NGOs.
|
-
Tripartite
approach between DAR,NIA, and DPWH implemented and fostered.
-
LGUs
support is sufficient for operation and maintenance of
infra facilities .Indicator: inflation rate remains stable
in single digit.
|
| Results
1. Rural infrastructure better supports farmer productivity
and welfare in the 79 target ARCs. |
-
79
CIPs/CISs, 327 kms of roads, 45 post harvest facilities
constructed/rehabilitated and operating effectively.
-
14,574
hectares irrigated.
-
Operation
and maintenance of all infrastructure routinely budgeted
and carried out.
-
Increased
volume of traffic in ARC.
-
15%
reduction in transport costs due to roads and bridges.
-
Percentage
increase in sales prices/value added due to improved post-harvest
infrastructure.
-
Routine
maintenance of infra by LGUs and POs.
|
-
Final
inspection and project completion reports.
-
Quarterly
monitoring of PPMOs and RPMOs.
-
Progress
and PBME reports.
-
Progress
and PBME reports.
-
Turn-over
documents between the project and LGUs/IAs/Coops
-
Final
inspection and project completion reports.
|
-
Water
resources are adequate and sustainable.
-
Infrastructure
facilities are well designed and constructed.
-
Agencies
are effective in implementation.
|
| 2.
Agricultural productivity and incomes are increase in a sustainable
way in 79 target ARCs. |
-
Increase
yield in palay/corn by 70% in end of project (2002).
-
Increase
cropping intensity by 200% in 2002.
-
Increase
effective crop area planted to palay to: 730 hectares
in 1998;
5,830 hectares in 1999;
8,740 hectares in 2000;
11,660 hectares in 2001;
14,574 hectares in 2022.
-
Increase
in percentage of value added within ARCs due to drying
and storage facilities.
|
|
-
Extreme
climate conditions depress rain fed yields or cause flooding
in irrigated areas.
-
Tripartite
approach to project implementation is working.
-
MOA
conditions adhered to and equity participation provided.
|
3.
Institutional Development
3.1 Organization/Coop improved their organization at management
3.2 Coop resources managed properly.
3.3 Transformation of organizations into credit worthy cooperatives.
3.4 Cooperative gainfully managing social enterprises.
3.5 Organization/Cooperative properly managing & operations
the PHF and irrigation for sustainability |
3.1
At least 90% of coops/organization improved their membership,
affiliation, PSPs and plans & programs.
3.2 At least 60% of coops is improved their CBUs, savings
and COMAT.
3.3 100% of cooperatives assisted under the project with established
linkage (with other organizations,i.e LGUs,NGOs, secondary/tertiary
coops and private sectors.
3.4 At least 80% of coops operating & managing agri-based
enterprises including services.
3.5 100% of organizations utilizing the PHF for drying and
storage; at least 50% of organization utilizing the PHF for
business purposes (palay trading, rice milling, etc. );
100% of organizations trained in O & M of facilities. |
3.1
NGO reports; PPMO reports
3.2 NGO reports;PPMO reports
3.3 NGO reports
3.4 NGO/PPMO reports
PPMO reports
3.5 PPMO reports
NGO reports |
|
| Outputs
1. Infrastructure development
1.1 Implementation manual prepared
1.2 Infrastructure components programmed based on ARISP-ARC
Development Flow.
1.3 Feasibility studies and development plans of infrastructure
support projects updated/prepared.
1.4 MOAs with IAs, Coops, and LGUs signed.
1.5 Detailed engineering designs, estimates and program of
works prepared.
1.6 Training/orientations for line-agencies conducted.
1.7 Infrastructure facilities constructed.
1.8 Final inspection and turn-over of facilities to IAs, Coops
and LGUs conducted.
1.9 Routine maintenance carried out by beneficiaries. |
1.1 Implementation manual prepared
1.2 Interventions incorporated into work plan, line-agencies
work plan and 79 ARC
development plan prepared.
1.3 245 Feasibility studies and development plans reviewed
by CPMO.
1.4 MOAs signed/executed for 245 projects.
1.5 Engineering designs, estimates and program of work prepared
for 245 projects.
1.6 Line-agencies able to make efficient/ sound design &
implement infrastructure projects.
1.7 79 Communal Irrigation Projects/Systems constructed or
rehabilitated, effectively operating and turned-over to Irrigators
Associations (IAs).
-
327
Kms of farm-to-market roads constructed or rehabilitated,
effectively operating and turned-over to LGUs/POs.
-
45
new- post harvest facilities constructed, effectively
operating and turned-over to cooperatives/IAs, to increase
in product prices due to out-of-season sale.
-% decrease in post-harvest losses.
1.8 245 projects turned-over to IAs, coops and LGUs.
1.9 At least 80% of projects maintained by IAs, coops and
LGUs. |
1.1 Manual
1.2 Global Work plan, line-agencies WFP, ARC development plan.
1.3 FS and development plans review results.
1.4 MOAs with IAs, coops and LGUs.
1.5 approved D/D and POWs
1.6 Progress reports, monitoring reports.
1.7 Monitoring and evaluation reports, project progress reports
submitted by PPMOs & RPMOs and line-agencies.
1.8 POs progress report
1.9 PBME reports |
-
Facilities
are designed and constructed according to project specifications.
-
Timely
availability of GOP, equity and maintenance funds
Land/right
of way are provided by beneficiaries
-
Line-agencies
are effective in implementation
-
IAs/POs
were involved prior to implementation
-
LGUs/Coops/IAs
undertake O & M responsibilities.
|
| 2.
Institutional Development
2.1 Key progress and impact indicators for M&E established
2.2 Action plans for institutional development based on ARC
development plan prepared.
2.3 Action plans implemented.
2.4 Update annual work plan for institutional development. |
2.1
M&E reports for institutional development prepared.
2.2 interventions incorporated into Global Work plan and Umbrella
NGO's WFP.
-
79
Action plan for institutional development proposal
2.3 79 IAs organized and mobilized to operate and maintain
the irrigation facilities.
-
63
organizations/coops established and strengthened to manage
the post-harvest facilities.
2.4 Annual work plan implemented. |
2.1
Project progress, monitoring and evaluation results.
2.2 Global work plan;Umbrella NGO's work plan;PPMO;WFP.
2.3 Progress reports, monitoring and evaluation results.
2.4 Annual work plan and budget. |
. |
| 3.
Project Management, Monitoring and Evaluation
3.1 Planning Phase
3.1.1 Project Management Offices at the provincial, regional
and central office mobilized.
3.1.3 Baseline survey conducted
3.1.4 ARC development planning in 79 ARcs prepared
3.1.5 Convert results of ARC development planning into costed
interventions for global work plan.
3.1.6 Global work plan submitted. |
3.1.1
PPMOs/RPMOs/CPMOs within DAr, NIA and DPWH established and
operating
3.1.2 Vehicles and equipment procured implementation manual
prepared and circulated.
3.1.3 Progress and impact monitoring reports prepared &
submitted using the indicators established for all components
3.1.4 79 ARISP-ARC development plans approved & implemented.
3.1.5 Interventions for all components identified and qualified
for 5 years.
3.1.6 Global work plan approved by project coordinating council;
submitted to DBM. |
3.1.1
Special Orders issued and project management reports submitted.
3.1.2 Implementation Manual3.1.3 Baseline survey results
3.1.4 ARISP-ARC development plans
3.1.5 Global work plan;Annual WFPs
3.1.6 Global work plan, Annual WFPs |
|
| Implementation
3.2.1 Progress reporting
3.2.2 Financial management
3.2.3 Project Administration
3.2.4 Key indicators monitored |
3.2.1
Timely submission of monthly, quarterly and annual progress
reports
3.2.2 Timely release of funds/Timely submission of SOEs.
3.2.3 Project accounting, filling and admin organized and
up-to-date.
3.2.4 Monitoring and Evaluation implemented comprehensively
on agreed indicators. |
3.2.1
Monthly, quarterly, annual progress reports3.2.2 LAA and Cash
releases SOEs
3.2.3 Project accounts;MIS and other admin records/journals.
3.2.4 Project progress and monitoring. |
. |
| Phase
Out
3.3.1 Conduct Impact Assessment
3.3.2 Ensure sustainability of all programs and projects.
3.3.3 Finalize Project Completion Report. |
3.3.1
Impact are assessed and positive conclusions drawn
3.3.2 All interventions on their effects and self-sustaining
after the project.
3.3.3 Completion report submitted and approved |
3.3.1
Projects internal impact assessment/surveys
3.3.2 Project final review and evaluation
3.3.3 Project completion report. |
. |