Status
-
Time elapsed
100%
- Physical Performance 110.74%
- Utilization Rate 100%
- Availment Rate 52%
1. Policy Component
2. Support Services Component
Basic Infrastructure
-
Completed
19 basic infrastructure projects (i.e. , FMR, road
rehabilaitation, construction of warehouse, solar
dryer)
Basic Social Services
- Completed eight (8)3 basic
social services projects (i.e., electrification, spring
development, barangay site development, construction
of deepwell and MPB)
|
|
|
| Social
Institutional Building and Strengthening
Social Institutional Building
and Strengthening
Agri-Productivity
-
Completed 35 agricultural productivity projects
(i.e., cattle/goat dispersal, distribution of farm
implements)
-
Distributed 280 carabaos and 618 farm implements
in Malita and Matanao CADC
-
Purchased 75 heads of fatteners and 35 heads of
goats (for breeding purpose)
-
Two (2) weighing scale
-
Two (2) corn sheller
-
Eighty (80) bags of corn seeds dispersed
-
Established rubber trees nursery
-
Developed 20 has. for durian production
3.
Organization and Management
-
80 field visits/monitoring
-
328 requests proposal
-
61 consultation/meeting/workshops attended and
conducted
|
|
|